  • Client: Siemens, Germany
  • Owner: Water and Power Development Authority (WAPDA)
  • Location: Pakistan
  • Description of Works: 02 Nos. Gas Turbines 100 MW each.
  • 01 No. Steam Turbine.

  • * Complete mechanical assembly erection, including piping, steel structure & allied equipment.
  • * Fabrication of HRSG all non pressure parts including ducts, stacks & steel structure.
  • Manhours: 0.4 million
  • Peak Manpower: 250
  • Completion: December 1992