Interceptor
SENIOR MEMBER
- Joined
- Apr 9, 2007
- Messages
- 2,005
- Reaction score
- 0
- Client: Siemens, Germany
- Owner: Water and Power Development Authority (WAPDA)
- Location: Pakistan
- Description of Works: 02 Nos. Gas Turbines 100 MW each.
- 01 No. Steam Turbine.
- * Complete mechanical assembly erection, including piping, steel structure & allied equipment.
- * Fabrication of HRSG all non pressure parts including ducts, stacks & steel structure.
- Manhours: 0.4 million
- Peak Manpower: 250
- Completion: December 1992
http://descon.com/Sectors/Power/mWCombinedCyclePowerPlant.aspx
This is a tragedy, the initial project was 21 power station for Pakistan, for the growing energy need the companies were kicked out of Pakistan by NS damn Pakistan, if all 21 would have been built Pakistan would be in a better posistion if they were completed.